New Jersey Turnpike Authority
Construction Industry Advancement Program
Working with New Jersey Turnpike Authority
Bridge Projects
William Wilson P.E.,
Supervising Engineer, Structures
November 19, 2009
BRIDGE CONSTRUCTION PROJECTS
BRIDGE CONSTRUCTION PROJECTS
Consists of:
– 10 Year Capital Construction Projects
– Annual Maintenance Projects
2010/2011 CONTRACTS TO
BE AWARDED
• Funding Sources
• Construction Type
• Construction Costs
2010 - CONTRACTS TO BE AWARDED
Bridge Construction Projects
NUMBER OF
CONTRACTS
CONTRACT
DESCRIPTION
CONSTRUCTION
ESTIMATE
3
BRIDGE WIDENING & REHABILITATION
$ 145 M
1
BRIDGE DECK RECONSTRUCTION
$ 85 M
1
BRIDGE REPLACEMENT
$ 15 M
1
BRIDGE PAINTING
$6M
2
BRIDGE SECURITY
$ 60 M
4
BRIDGE REPAIRS & RESURFACING
$ 35 M
TOTALS =
$ 346 M
2010 - CONTRACTS TO BE AWARDED
Bridge Construction
Capital Projects
•
T100.147 - Repainting Structural Steel, Structure Nos. 84.24 N & S – 1st Quarter
2010
•
T100.034 - Bridge Deck Reconstruction, Miscellaneous Structural, Roadway and
Lighting, Improvements, Milepost N0.00 to N3.00 – 1st Quarter 2010
•
A100.183 – TPK/GSP Major Bridge Perimeter Security & Access Restriction
Improvements – 3rd Quarter 2010
•
P100.124 - Replacement of the Watchung Avenue Bridges at Milepost 152.4 – 4th
Quarter 2010
•
P100.132 - Widening and Rehabilitation of the Patcong Creek Bridge at GSP
Milepost 31.0 – 4th Quarter 2010
•
P100.130 - Widening and Rehabilitation of the Bass River Bridge at Milepost 51.9 4th Quarter 2010
•
P100.025 – Rehabilitation of the Mullica River Bridge at Milepost 49.0 - 4th Quarter
2010
•
A100.XXX – TPK/GSP Bridge Security Improvements, CM/GC – 4th Quarter 2010
2010 - CONTRACTS TO BE AWARDED
Bridge Construction
Annual Maintenance Projects
•
T100.106 - Bridge Deck Repairs and Resurfacing, Milepost 83 to 122 and the NBHCE – 4th Quarter 2009
•
P100.079 - Bridge Repairs and Resurfacing, Milepost 0 to 126 – 4th Quarter 2009
•
T100.107 - Bridge Repairs and Resurfacing, Milepost 0 to 122, the NB-HCE and the
PHMTE – 1st Quarter 2010
•
P100.108 - Bridge Repairs and Resurfacing, Milepost 126 to 172 - 1st Quarter 2010
2011 - CONTRACTS TO BE AWARDED
Bridge Construction Projects
NUMBER OF
CONTRACTS
CONTRACT
DESCRIPTION
CONSTRUCTION
ESTIMATE
2
BRIDGE DECK RECONSTRUCTION
$ 170 M
1
BRIDGE PAINTING
$ 25 M
2
BRIDGE SECURITY
$ 60 M
1
SPECIALIZED STRUCTURAL REPAIRS
$ 10 M
4
BRIDGE REPAIRS & RESURFACING
$ 35 M
TOTALS =
$ 300 M
2011 - CONTRACTS TO BE AWARDED
Bridge Construction
Capital Projects
•
T100.137 - Easterly Hackensack River Bridge Deck Reconstruction, Structure No.
E109.83 – 1st Quarter 2011
•
•
P100.132 – Substructure and Pile Repairs – 1st Quarter 2011
T100.125 - Bridge Deck Reconstruction And Miscellaneous Improvements, NB-HCE,
Milepost N6.00 to N8.20 – 2nd Quarter 2011
•
P100.XXX - Repainting Structural Steel, Structure Nos. 127.2N – 2nd Quarter 2011
•
A100.XXX – Bridge Security
•
A100.XXX – Bridge Security, CM/GC
2011 - CONTRACTS TO BE AWARDED
Bridge Construction
Annual Maintenance Projects
•
T100.XXX - Bridge Deck Repairs and Resurfacing, Milepost 83 to 122 and the NBHCE – 4th Quarter 2010
•
P100.XXX - Bridge Repairs and Resurfacing, Milepost 0 to 126 – 4th Quarter 2010
•
T100.XXX - Bridge Repairs and Resurfacing, Milepost 0 to 122, the NB-HCE and the
PHMTE – 1st Quarter 2011
•
P100.XXX - Bridge Repairs and Resurfacing, Milepost 126 to 172 - 1st Quarter 2011