Document 7741878

Download Report

Transcript Document 7741878

SLAC
LAT Meeting
17Jul 2003
GLAST Calorimeter
SLAC Meeting
Calorimeter Subsystem
17 July 2003
W. N. Johnson
Naval Research Lab
wnjohnson
1
Naval Research Lab
Washington DC
GLAST Calorimeter







Outline
SLAC
LAT Meeting
17Jul 2003
Current Status
Interdependencies with other Subsystems
Flight hardware procurements
Engineering Model Testing Closure
Greatest Risks to Schedule
Unresolved Assumptions
Critical Path – key drivers
wnjohnson
2
Naval Research Lab
Washington DC
GLAST Calorimeter

Current Situation
SLAC
LAT Meeting
17Jul 2003
Absorption of original French Work
 Revised MoA with IN2P3 has been signed.
 Drawings have been translated to English. Most are ready for release. Critical
titanium parts are in manuf.
 Side plates will be purchased from France
 Baseplate delayed in CAL-Grid I/F redesign and assoc analyses
 CDE bonding team in place at Swales. Test bonding has begun. Flight qual
tooling is being manufactured.
 PDA manufacturing tooling in design, process specification is being updated.
Requirements have been discussed with potential vendors. RFQ has not been
released

ASIC GCFE ver 9A has been submitted. Out of fab 9/17/03
 GCRC5 working on EM w/ GCFE7 does not work well at 20 MHz. Problems
are being investigated
 EM EMI/EMC testing indicate need for better test configuration and test
plans. Don’t know if they show design problem in CAL.
wnjohnson
3
Naval Research Lab
Washington DC
Interdependencies with other
GLAST Calorimeter
LAT components

SLAC
LAT Meeting
17Jul 2003
Resolve and verify CAL – Grid interface
 Complete analyses. Detail extra features – cable tray attachment
 Release IDDs or whatever


Resolve and verify CAL – T&DF box mechanical, thermal design,
and EMI/EMC design.
Identify, cost and schedule needed TEM and PS (EM2??) that
supports the compressed CAL assembly and test schedule.
 Improve documentation and procedures

Produce EEE Parts required documentation (as identified by
GSFC) for the ASICs or tell them NO and resolve the qualification
of the ASICs for flight.
wnjohnson
4
Naval Research Lab
Washington DC
GLAST Calorimeter

SLAC
LAT Meeting
17Jul 2003
Flight Hardware
Procurements
Except for new work in US, most flight procurements are made or are in
process.
 EEE parts complete except for uncertainty on some PPL resistors.
 AFEE – TEM interconnect cable order needs design verification and EEE parts
test agreement.
 AFEE PCB is in design modification.

CDE manufacturing contract in place – Swales
 PDA manufacturing spec is in development – outside vendor, GFE’ed to
Swales.
 Plan CDE Manufacturing Readiness Review in August.

Metallic machined parts from NRL.
 Awaiting revised drawings of baseplate.
 Potential issues relative to recent EMI/EMC testing – surface treatment, more
screws

Plastic and Elastomeric parts for CDE – structure interface at LLR
 Specs in place, vendors selected, parts approved.
 First procurements in place.
wnjohnson
5
Naval Research Lab
Washington DC
GLAST Calorimeter
Mass Properties
Comprehensive
Performance Test
(LAT-PS-01371-01)
Cycle
(1Thermal
atmosphere)
Comprehensive


Thermal Vacuum
Testing
Vibration Testing
Aug 8
Ship to SLAC
(LAT-PS-01347-01)
(LAT-PS-01346-01)
12 Thermal Cycles
Sine Sweep
(Limited & Comprehensive
Performance Tests
throughout)
LAT Testing at SLAC
Burn-In
Return EM to NRL
Oct 15
Limited
Performance Test
Random
Limited
Performance Test
Comprehensive
Performance Test

Beam Test at GSI
Nov 14
(LAT-PS-01371-01)
Sine Burst
Performance Test
(LAT-PS-01371-01)
Comprehensive
Performance Test
Swap TEM/PS
Install GCRC5


EMI/EMC Testing
(LAT-PS-01371-01)
wnjohnson
SLAC
LAT Meeting
17Jul 2003
Engineering Model
Testing Closure
(LAT-PS-01513-01)
6
Support Flight
Production at NRL
and SLAC

Dec 25
Additional Beam
Tests, etc
Naval Research Lab
Washington DC
GLAST Calorimeter





wnjohnson
Greatest Risks to Schedule
SLAC
LAT Meeting
17Jul 2003
ASIC acceptability for flight – both performance and
qualification.
CDE Bonding process development and qualification
delay.
Ability of Sweden to maintain the delivery rate and
schedule of CsI crystals.
EEE parts use approval and impact on assembly of
AFEE board.
Failure or process problem in module assembly or test
which stops the production pipeline.
7
Naval Research Lab
Washington DC
CAL Revised Summary Schedule
GLAST Calorimeter
SLAC
LAT Meeting
17Jul 2003
Module Available
Dates (RFI)
Module Need
Dates (RFI)
wnjohnson
8
Naval Research Lab
Washington DC
GLAST Calorimeter

Unresolved Assumptions
SLAC
LAT Meeting
17Jul 2003
CAL will receive 18 Flight TEM and Power Supplies that are fully tested and ready
for integration with CAL flight hardware.



Required EGSE for functional testing of TKR side of TEM will be provided.
Required Test scripts for testing of TKR side of TEM will be provided.
TKR simulation configuration (whatever is required) will meet environmental test
requirements – TVAC, EMI/EMC(?), Vib
–
–


mechanical support of connector savers during vib?
Cable lengths or mounting of simulators
Capable of surviving CAL Vibration Test levels
Capable of providing appropriate EMI/EMC test environment.

~5 EM1 or EM2 TEM boards (unpackaged?) to support AFEE card assembly and
test
 CAL will receive sufficient VME Interface Cards (COMM & PDU?) and PowerPCs to
support XX CAL Test Stands



10 CTS to support module Assy & Test
6 mini CTS to support AFEE card assembly and test - minimal config, power control not
needed.
EGSE communications (COMM to/from TEM) can support required cable lengths
for TVAC and EMI/EMC testing over temperature – 10 m or more with bulkhead
connector adaptors.
wnjohnson
9
Naval Research Lab
Washington DC
GLAST Calorimeter
SLAC
LAT Meeting
17Jul 2003
AFEE Board Burn-In EGSE
THERMAL CHAMBER
7
8
13
2
AFEE 3.3VDC
VME CRATE
MDM69R
Power Supply
(DC)
10
DB9P DB9S
6
MDM69R
Transition
Board
5
3
PWR
MDM69R MDM69P
MDM69R MDM69P
TEM
EGSE
MDM25 MDM25
HD78S
MDM69P
12
11
GASU
MDM51R MDM51P
UPS
AFEE
+X, 0,
Side
TEM GSE 3.3VDC
HD78P
MDM69P
AFEE
+Y, 1,
Side
MDM69R MDM69P
AFEE MDM69R
MONITOR
MDM69R MDM69P
MDM69R MDM69P
MDM69P
MDM69R MDM69P
MDM69R MDM69P
MDM69R MDM69P
MDM69R
AFEE
-X, 2,
Side
MDM69P
MDM25 MDM25
MDM69R MDM69P
MDM69R MDM69P
4
CMD
PWR
PC
Event
Monitor
LCB
DB50P/DB50S
9
15
MDM25 MDM25
MDM25 MDM25
CAT-5
HUB
Ethernet
MDM69R MDM69P
MDM69R
MDM69P
AFEE
-Y, 3,
Side
14
MVME
2306
Fluke
NetDaq
2640
16
PWR
PWR
Ethernet
PWR
PWR
13
8
7
2
AFEE
+X, 0,
Side
17
VME CRATE
MDM69R
Power Supply
(DC)
10
MDM69R
Transition
Board
MDM69R MDM69P
TEM
EGSE
5
3
PWR
12
11
DB9P DB9S
GASU
6
UPS
MDM69P
MDM25 MDM25
MDM69R MDM69P
MDM69P
AFEE
+Y, 1,
Side
MDM69R MDM69P
AFEE MDM69R
MONITOR
MDM69R MDM69P
MDM69R MDM69P
MDM69P
MDM69R MDM69P
MDM69R MDM69P
MDM69R MDM69P
MDM69R
AFEE
-X, 2,
Side
MDM69P
MDM25 MDM25
Monitor
MDM69R MDM69P
CMD
PWR
PC
MDM69R MDM69P
MDM69R MDM69P
Event
4
LCB
15
MDM25 MDM25
14
MVME
2306
Fluke
NetDaq
2640
PWR
PWR
AFEE
-Y, 3,
Side
NEED: 4 – 5 AFEE
Board Test Stands
MDM69R
MDM25 MDM25
CAT-5
HUB
DB50P/DB50S
9
MDM69P
PWR
PWR
Ethernet
wnjohnson
10
Naval Research Lab
Washington DC
TVAC EGSE Config – 2 Modules
GLAST Calorimeter
SLAC
LAT Meeting
17Jul 2003
37-PIN Bulkhead
Feedthrough Connectors
(Thermal Vacuum
Compatible)
Thermal Vacuum Chamber
2
8
9
VME CRATE
1
GASU TV
5
Power Supply
(DC)
97-3106A-28-21P
97-3106A-28-21S
97-3106A-28-21P
44
28VDC Power Harness
GASU TV
GASU TV
22
22
14
MDM51 MDM51
UPS
44
6
3
PWR
97-3106A-28-21S
7
Transition
Board
10
PDU TV
16
CAL
Module
[1 of 2]
15
25
13
PDU TV
MDM25 MDM25
HD78S
HD78P
97-3106A-28-21S
97-3106A-28-21P
22
25
MDM25 MDM25
Monitor
TEM
Event
PWR
16
LCB
CMD
4
PC
PSA
MDM25 MDM25
HD78S
CAT5 Ethernet
MDM25 MDM25
12
MDM51 MDM51
HD78P
MVME
2306
Deutsch - 37D Male
11
17 Deutsch - 37D Female
18
PWR
PWR
8
2
9
VME CRATE
1
14
22
5
Power Supply
(DC)
CAL
Module
[2 of 2]
15
28VDC Power Harness
GASU TV
97-3106A-28-21S
97-3106A-28-21P
97-3106A-28-21S
97-3106A-28-21P
44
22
MDM51 MDM51
44
UPS
6
Transition
Board
16
3
16
PDU TV
MDM25 MDM25
7
PWR
HD78S
HD78P
22
13
GASU TV
10
TEM
MDM51 MDM51
12
25
25
97-3106A-28-21S
97-3106A-28-21P
PSA
PDU TV
HD78S
HD78P
MDM25 MDM25
PC
11
Event
4
PWR
CMD
Monitor
MDM25 MDM25
CAT5 Ethernet
NEED Peak of 10 Complete
Cal Test Stands (CTS)
LCB
MDM25 MDM25
MVME
2306
PWR
PWR
wnjohnson
11
Naval Research Lab
Washington DC
GLAST Calorimeter
Dual PIN
Photodiode
NRL, CEA/Salcay
06/18/03 (29)
10/28/03
Crystal Detector
CDE Bonding
Elements (CDE)
CEA/Saclay
09/26/03 (-18)
CsI Crystals
Sweden
05/16/03 (50)
June ’03 Needs Assessment
Pre Electronics
Module
NRL
11/04/03 (-18)
Carbon Composite Structure
Al base, closeouts, plastic parts
LLR/Ecole Polytechnique
07/24/03 (30)
ASICs
SLAC, NRL
08/08/03 (1)
11/15/03
Another Fab
Critical Path
10/15/03
Baseplate
Other EEE parts
Parts Qual/Screen
NRL
08/08/03 (1)
Analog Front End
Electronics (AFEE)
NRL
10/09/03 (1)
~1/15/04
Calibration
Environmental Test
NRL
03/04/04 (-27)
PCB
NRL, SLAC
07/11/03 (12)
Completion Dates (float)
wnjohnson
SLAC
LAT Meeting
17Jul 2003
Critical Path (CDR)
Qual Module (FMA)
12
Critical Path in Red
CAL Module
NRL
12/16/03 (-18)
~2/20/04
BIG ERROR
3/16/04
~5/20/04
Ready for
Integration (RFI)
03/25/04 (-27)
(L3: 02/17/04)
BIG ERROR
7/02/04
Naval Research Lab
Washington DC
GLAST Calorimeter
wnjohnson
New Module RFIs ???
13
SLAC
LAT Meeting
17Jul 2003
Naval Research Lab
Washington DC
GLAST Calorimeter
wnjohnson
CAL Milestones Lvl 3 & 4
14
SLAC
LAT Meeting
17Jul 2003
Naval Research Lab
Washington DC