The LHC Challenge on Beam Loss and Collimation R. Assmann, CERN/AB 16/08/2007 for the Collimation Team SLAC RWA, SLAC 8/07
Download ReportTranscript The LHC Challenge on Beam Loss and Collimation R. Assmann, CERN/AB 16/08/2007 for the Collimation Team SLAC RWA, SLAC 8/07
The LHC Challenge on Beam Loss and Collimation R. Assmann, CERN/AB 16/08/2007 for the Collimation Team SLAC RWA, SLAC 8/07 Outline 1) Introduction: The LHC Challenge 2) LHC Collimation Basics 3) Collimator Hardware 4) Collimation Performance 5) Tunnel Installations 6) Collimator Beam Tests 7) Beyond Phase 1 8) Conclusions RWA, SLAC 8/07 2 1) Introduction: The LHC Challenge The Large Hadron Collider: Circular particle physics collider with 27 km circumference. Two colliding 7 TeV beams with each 3 × 1014 protons. Super-conducting magnets for bending and focusing. Start of beam commissioning: May 2008. LHC nominal parameters Particle physics reach defined from: 1) Center of mass energy 14 TeV super-conducting dipoles Number of bunches: Bunch population: Bunch spacing: 2808 1.15e11 25 ns Top energy: Proton energy: Transv. beam size: Bunch length: Stored beam energy: 7 TeV ~ 0.2 mm 8.4 cm 360 MJ Injection: 2) Luminosity RWA, SLAC 8/07 1034 cm-2 s-1 Proton energy: Transv. Beam size: Bunch length: 450 GeV ~ 1 mm 18.6 cm 3 LHC Luminosity • Luminosity can be expressed as a function of transverse energy density re in the beams at the collimators: d = demagnification (bcoll/b*) Np = protons per bunch frev = revolution freq. Eb = beam energy • Various parameters fixed by design, for example: – Tunnel fixes revolution frequency. – Beam-beam limit fixes maximum bunch intensity. – Machine layout and magnets fix possible demagnification. – Physics goal fixes beam energy. • Luminosity is increased via transverse energy density! RWA, SLAC 8/07 4 Transverse Energy Density 1 GJ/mm2 1 MJ/mm2 Parameter for material damage: re LHC advancement: Factor 7 in beam energy Factor 1000 in re RWA, SLAC 8/07 5 Stored Energy LHC stored energy corresponds to 80 kg TNT per beam! Dangerous beam! RWA, SLAC 8/07 6 Proton Losses • LHC high power beams: – Ideally no power lost (protons stored with infinite lifetime). • Collimators are the LHC defense against unavoidable losses: – Irregular fast losses and failures: Passive protection. – Slow losses: Cleaning and absorption of losses in super-conducting environment. – Radiation: Managed by collimators. – Particle physics background: Minimized. 1% of beam over 10s peak loss • Realistically: – Slow losses: 0.5 – 1.0 MW onto collimators – Fast losses: up to 1 MJ in 200 ns into 0.2 mm2 RWA, SLAC 8/07 (up to 10 s) 7 Preventing Quenches • Shock beam impact: 2 MJ/mm2 in 200 ns (0.5 kg TNT) • Maximum beam loss at 7 TeV: 1% of beam over 10 s 500 kW • Quench limit of SC LHC magnet: 8.5 W/m RWA, SLAC 8/07 8 Machine Protection • There are a number of LHC failure scenarios which lead to beam loss. • No discussion of machine protection details here. However, comments on collimator role in machine protection. • Slow failures: – First losses after >50 turns appear at collimators as closest aperture restrictions. – Beam loss monitors detect abnormally high losses and dump the beam within 1-2 turns. • Fast failures (dump and injection kicker related): – Sensitive equipment must be passively protected by collimators. • In all cases, the exposed collimators must survive the beam impact: up to 2 MJ in 200 ns (0.5 kg TNT) RWA, SLAC 8/07 9 The LHC Collimation Project • 2002: Conclusion that the originally foreseen LHC collimation system would not withstand the LHC intensities and not provide sufficient cleaning and protection. • 2003: Start of LHC collimation project to urgently provide: – robust collimator hardware design. – suffcient cleaning efficiency and protection. – hardware R&D and prototyping. – prototype testing without and with beam. – industrial production and installation. • In view of technical challenge and short time available, implementation of staged approach. Collaborative approach to include world-wide expertise. • Total investment cost of ~28 M$ plus about 90 man-years CERN staff. • Quite a strong effort over the last 4.5 years! RWA, SLAC 8/07 10 The Collimation Team… Collimation team: About 60 CERN technicians, engineers and physicists… in various groups and departments. + many friends in connected areas (BLM’s, MP, …) + collaborators in various laboratories (SLAC, FNAL, BNL, Kurchatov, …) RWA, SLAC 8/07 11 The Staged LHC Path Energy density at collimators Stored energy in beams Number of collimators (nominal 7 TeV) State-of-the-art in SC colliders (TEVATRON, 1 MJ/mm2 2 MJ Phase 1 LHC Collimation 400 MJ/mm2 150 MJ 88 Nominal LHC 1 GJ/mm2 360 MJ 122 Ultimate & upgrade scenarios ~4 GJ/mm2 ~1.5 GJ ≤ 138 Limit (avoid damage/quench) ~50 kJ/mm2 ~10-30 mJ/cm3 HERA, …) Factor >1000 Equivalent 80 kg TNT explosive RWA, SLAC 8/07 12 2) LHC Collimation Basics RWA, SLAC 8/07 13 LHC Need for Collimation • Ideally, stored proton beams would have infinite lifetime and no protons would be lost. • However, a multitude of physical processes will limit the lifetime of the beams and unavoidable proton losses must be taken into account. • Conditions for quenching the SC magnets: – Transient loss of 10-9 fraction of beam (within 10 turns) – Slow loss of 3×10-8 fraction of beam per s and per m (< 10000 h lifetime) • Proton losses must be intercepted and absorbed by specifically designed devices, namely collimators. These constrain the aperture. • Multi-turn process: protons diffuse to limiting aperture bottleneck. Process also called beam cleaning. • 2 out of 8 straight sections in the LHC are dedicated to collimation! RWA, SLAC 8/07 14 Multi-Stage Cleaning & Protection Beam axis Beam propagation Impact parameter Core Collimator Particle Unavoidable losses CFC RWA, SLAC 8/07 CFC e Absorber e p Shower Secondary collimator Primary collimator Impact parameter ≤ 1 mm Secondary p halo p Shower p W/Cu Tertiary halo p Superconducting magnets Absorber Primary halo (p) SC magnets and particle physics exp. W/Cu 15 Diffusion Process & Impact Parameter Slow loss: Uniform “emittance” blow-up Beam lifetime: 0.2 h Loss rate: Loss in 10 s: 4.1e11 4.1e12 p/s p (1.4 %) (~ 40 bunches) Assume drift: 0.3 sig/s 5.3 nm/turn (sigma = 200 micron) Transverse impact parameter Almost all particles impact with y ≤ 0.2 mm Surface phenomenon! RWA, SLAC 8/07 16 “Phase 1” System Design Momentum Collimation Betatron Collimation “Final” system: Layount is 100% frozen! RWA, SLAC 8/07 C. Bracco 17 LHC Collimator Gaps Collimator settings: 5 - 6 s (primary) 6 - 9 s (secondary) s ~ 1 mm (injection) s ~ 0.2 mm (top) Small gaps lead to: 1. Surface flatness tolerance (40 mm). 2. Impedance increase. 3. Mechanical precision demands (10 mm). RWA, SLAC 8/07 18 Required Efficiency Quench threshold Allowed intensity (7.6 ×106 p/m/s @ 7 TeV) Illustration of LHC dipole in tunnel N max p Rq Ldil /c Cleaning inefficiency = Number of escaping p (>10s) Number of impacting p (6s) Beam lifetime (e.g. 0.2 h minimum) Dilution length (~10 m) Collimation performance can limit the intensity and therefore LHC luminosity. RWA, SLAC 8/07 19 Intensity Versus Cleaning Efficiency For a 0.2 h minimum beam lifetime during the cycle. 99.998 % per m efficiency RWA, SLAC 8/07 20 The LHC Phase 1 Collimation • Low Z materials closest to the beam: – Survival of materials with direct beam impact – Improved cleaning efficiency – High transparency: 95% of energy leaves jaw • Distributing losses over ~250 m long dedicated cleaning insertions: – Average load ≤ 2.5 kW per m for a 500 kW loss. – No risk of quenches in normal-conducting magnets. – Hot spots protected by passive absorbers outside of vacuum. • Capturing residual energy flux by high Z absorbers: – Preventing losses into super-conducting region after collimator insertions. – Protecting expensive magnets against damage. • No shielding of collimators: – As a result radiation spread more equally in tunnel. – Lower peak doses. – Fast and remote handling possible for low weight collimators. RWA, SLAC 8/07 21 3) Collimator Hardware RWA, SLAC 8/07 22 Hardware: Water Cooled Jaw Up to 500 kW impacting on a jaw (7 kW absorbed in jaw)… Advanced material: Fiber-reinforced graphite (CFC) RWA, SLAC 8/07 23 The LHC “TCSG” Collimator 1.2 m 3 mm beam passage with RF contacts for guiding image currents Designed for maximum robustness: Advanced CC jaws with water cooling! Other types: Mostly with different jaw materials. Some very different with 2 beams! 360 MJ proton beam RWA, SLAC 8/07 24 Other collimator features • In-situ spare concept by moving the whole tank (move to fresh surface if we scratch the surface with beam) • Direct measurements of jaw positions and absolute gap (we always know where the jaws are) • Precision referencing system during production • Measurements of jaw temperature • Radiation impact optimization: Electrical and water quick plug-ins, quick release flanges, ceramic insulation of cables, ... • RF contacts to avoid trapped modes or additional impedance C. Rathjen, AT/VAC RWA, SLAC 8/07 25 Problem Collection I RWA, SLAC 8/07 TS/MME analysis of problems 26 Problem Collection II TCS010 after bake-out (8 Sep 2006) 1.00E-07 9.00E-08 Partial Pressure [uncalibrated] 8.00E-08 7.00E-08 6.00E-08 5.00E-08 4.00E-08 3.00E-08 2.00E-08 1.00E-08 0.00E+00 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 Mass RWA, SLAC 8/07 AT/VAC and TS/MME analysis of problems 27 RWA, SLAC 8/07 -06 06 -07 07 J an -0 8 De c-0 7 No v-0 7 Oc t- Se p- 0 7 Au g- 0 7 J ul J un -0 7 Ma y -0 7 Ap r- 0 7 Ma r- 0 7 Fe b- 0 7 J an -0 7 De c-0 6 No v-0 6 Oc t- Se p- 0 6 Au g- 0 6 J ul J un -0 6 Ma y -0 6 Ap r- 0 6 Ma r- 0 6 # collimators Production in Industry 110 collimators in industry + 26 collimators at CERN spares 120 100 80 60 40 20 0 Date 28 4) Collimation Performance RWA, SLAC 8/07 29 Massive Computing: Performance Simulations: 5 million halo protons 200 turns realistic interactions in all collimator-like objects LHC aperture model Multi-turn loss predictions RWA, SLAC 8/07 30 Efficiency in Capturing Losses Local inefficiency [1/m] Beam1, 7 TeV Efficiency 99.998 % per m TCDQ Betatron cleaning Ideal performance Quench limit (nominal I, =0.2h) Beam2, 7 TeV Efficiency 99.998 % per m TCDQ Betatron cleaning Ideal performance Quench limit (nominal I, =0.2h) 99.998 % Local inefficiency: #p lost in 1 m over total #p lost = leakage rate RWA, SLAC 8/07 31 Zoom Dispersion Suppressor IR7 Collimation team and FLUKA team mW Heat load showers RWA, SLAC 8/07 32 Can We Run at the Quench Limit? • BLM response depends on where the protons are lost! • Important shielding effect of materials. • Up to factor 10 different BLM response for different longitudinal locations! • BLM threshold must protect against quenches from all different loss locations. • Threshold at least factor 3 below quench limit (HERA factor 10). • We cannot run at quench limit! L. Ponce RWA, SLAC 8/07 33 K. Tsoulou et al Energy Deposition (FLUKA) FLUKA team RWA, SLAC 8/07 34 CERN Mechanical Simulations Displacement analysis – Nominal conditions (100 kW) – Load Case 2 10s Transient (500 kW) – Loss rate 4x1011 p/s (Beam Lifetime 12min) Initial loss 8e10p/s Max. deflect. ~20mm Transient loss 4e11p/s during 10s Max deflect. -108mm Back to 8e10p/s situation! RWA, SLAC 8/07 A. Bertarelli & A. Dallochio 35 Kurchatov Studies on Shock Waves One nominal p bunch impacts on the CFC collimator jaw: Evolution of shock wave… X-axis: Jaw length (0 to 150 cm) Y-axis: Pressure in 1012 erg/cm3 A. Ryazanov Compression area Relevant question: RWA, SLAC 8/07 570 ms 110 ms 250 ns Tensile area Interference of shock waves from different bunches, including reflections of shock waves at boundaries? 36 Local Activation • Losses at collimators generate local heating and activation. • Local heating: On average 2.5 kW/m. • Activation: Up to 20 mSv/h on contact (better not touch it). • Fast handling implemented. Remote handling being developed. Residual dose rates One week of cooling S. Roesler et al RWA, SLAC 8/07 37 Kurchatov Collaboration Studies of CFC Material Used in LHC Collimators A. Ryazanov Working on understanding radiation damage to LHC collimators from 1016 impacting protons of 7 TeV per year. Also with BNL/LARP… … in addition shock wave models… RWA, SLAC 8/07 38 Impedance Problem • Several reviews of LHC collimator-induced impedance (originally not thought to be a problem). • Surprise in 2003: LHC impedance driven by collimators, even metallic collimators. • LHC will have an impedance that depends on the collimator settings! • Strong effort to understand implications… Third look at impedance in Feb 03 revealed a problem: F. Ruggiero RWA, SLAC 8/07 39 Transverse Impedance [MΩ/m] First Impedance Estimates 2003 Typical collimator half gap 104 103 102 LHC impedance without collimators 10 1 10-1 0 2 4 6 Half Gap [mm] RWA, SLAC 8/07 8 10 F. Ruggiero, L. Vos 40 2006 Impedance Estimates E. Metral et al Limitation at about 40% of nominal intensity… (nominal b*, full octupoles) RWA, SLAC 8/07 Important: Collimator impedance was measured in the SPS with LHC prototype collimator. 41 Stability diagram (maximum octupoles) and collective tune shift for the most unstable coupled-bunch mode and head-tail mode 0 (1.15e11 p/b at 7 TeV) 25 ns Im Q Vertical plane 0.00005 UNSTABLE 0.00004 Effect of the bunch spacing… 0.00003 50 STABLE 0.00002 75 150 Re Q 0.001 RWA, SLAC 8/07 Single bunch 0.00001 300 0.0008 900 0.0006 0.0004 0.0002 42 Potential Solutions Impedance • Metallic secondary collimators (phase 2 design at SLAC and CERN) lower electrical resistivity of collimator “wall”. • Increased chromaticity stabilize beams. • Low noise transverse feedback at 7 TeV stabilize beams. • Larger collimator gaps: – Triplet upgrade with larger aperture. Collimator gaps at 7 TeV are a direct function of the triplet aperture and the b*, if efficiency is good enough. – Crystal-based collimation with increased particle deflection larger gaps for secondary collimators, if efficiency good enough. – Non-linear collimation scheme larger gaps for secondary collimators, if efficiency good enough. All approaches must be looked at, even if they now seem challenging! LARP/SLAC takes first steps towards construction of phase 2 collimator. RWA, SLAC 8/07 43 Opening Collimator Gaps Power Deposition [W/m] (dN/dt = 0.1% per s, lost at collimators, nominal intensity) Quench Limit TCP Setting [sigma] C. Bracco et al Higher losses in SC magnets close to cleaning insertions. RWA, SLAC 8/07 44 Impedance and Chromaticity E. Metral et al RWA, SLAC 8/07 45 5) Tunnel Installations RWA, SLAC 8/07 46 Collimator General Layout (vertical and skew shown) Water Connections Vacuum pumping Modules Collimator Tank (water cooled) Quick connection flanges A. Bertarelli RWA, SLAC 8/07 BLM Beam 2 47 Base Support and Lower Plug-In Guides Guides Water plugs Lower plug-in Electrical plugs Base support RWA, SLAC 8/07 48 Support & Plug-In Installation LSS5 Survey and alignment done with quick-plugin supports and without collimator (precise reference from plugin and alignment tool). RWA, SLAC 8/07 49 Collimator Installation Quick plug-in support (10 min installation) RWA, SLAC 8/07 50 Collimator Transport Vehicle Start of training for collimator installation with upgraded vehicle (K. Kershaw et al). RWA, SLAC 8/07 51 BLM’s for Observing Beam Loss Every collimator has 2 dedicated BLM’s. SEM: 0.05 charges per particle Ionization chamber: 500 particles per particle per cm traversal RWA, SLAC 8/07 52 6) Collimator Beam Tests in SPS RWA, SLAC 8/07 53 Collimator Controls S. Redaelli et al Collimator Beam-Based Alignment Successful test of LHC collimator control architecture with SPS beam (low, middle, top level) RWA, SLAC 8/07 54 Position Measurement and Reproducibility LVDT Calibration Repeatability test (TT40) 36 repetitions 1.01 1.005 20 µm 1 Normalized position [mm] 0.995 0.99 0.985 0.98 0.975 ~ 25 µm mechanical play 0.97 0.965 0.96 0.955 0.95 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 distance [mm] • Measured during test in TT40 (Oct. 31st) in remote!!!! RWA, SLAC 8/07 R. Losito et al 55 Typical beam loss signal for move of jaw Observation of BLM signal tails: BLM team: RWA, SLAC 8/07 Up to 10-20 seconds in length Many measurements Beam related true signal! 56 Loss Tails with Echo 12 s Another example Jaw movement C. Bracco, T. Weiler et al RWA, SLAC 8/07 Beam tails with long decay times (several 10 s) already shown in 2004! This time observation of “echo” in beam loss tails… 57 Collimator-Induced Tune Change (Changing Collimator Gap) Gap: 2.1 51 mm M. Gasior, R. Jones et al SPS tune depends on collimator gap! Expected tune change observed within factor 2! Impedance estimates are strongly confirmed by experiment! F. Zimmermann et al RWA, SLAC 8/07 58 2006 Impedance Measurement Improved controls in 2006: • Possibility of automatic scan in collimator position. • Much more accurate and complete data set in 2006 than in 2004! R. Steinhagen et al E. Metral et al RWA, SLAC 8/07 59 Microphone Robustness Test C-C jaw TED Dump C jaw 450 GeV 3 1013 p 2 MJ 0.7 x 1.2 mm2 ~ Tevatron beam ~ ½ kg TNT RWA, SLAC 8/07 • Jaw impact could be measured during all expected hits: no change in jaw dimensions (nothing fell off) • Closure of two jaws to 1mm gap after test. • Took out collimator last week and inspected (two months cooldown). • Microscopic analysis to be done. 60 Jaws after Shock Impact RWA, SLAC 8/07 61 Temperature Response TT40 collimator temperature probes 65.0 60.0 Spikes correspond to 2 MJ beam shock impact: Possibility to detect accidental beam impact! Temperature [°C] 55.0 50.0 Temp Upstream [°C] Temp Downstream [°C] Temp Water Cooling [°C] Temp Downstream [°C] Temp Water Cooling [°C] Temp Upstream [°C] 45.0 40.0 35.0 30.0 25.0 20.0 0:00 2:24 4:48 7:12 9:36 12:00 14:24 16:48 Time Elapsed [h:min] P. Gander et al RWA, SLAC 8/07 62 7) Beyond Phase 1 • The phase 1 system is the best system we could get within the available 4-5 years. • Phase 1 is quite advanced and powerful already and should allow to go a factor 100 beyond HERA and TEVATRON. • Phase 2 R&D for advanced secondary collimators starts early to address expected limitations of phase 1. • Phase 2 collimation project was approved and funded (CERN white paper). Starts Jan 2008. Should aim at complementary design compared to SLAC. • SLAC/LARP effort on rotatable collimator is a crucial contribution in our plans and addresses several possible problems. • Goal is to be ready for collimation upgrade in shutdown 2011/12, if needed. Base decision on phase 1 experience and results of phase 2 prototype tests. • We also revisit more advanced collimation schemes, like crystals, magnetic collimators, non-linear schemes. RWA, SLAC 8/07 63 Collimation Planning Phase 2 RWA, SLAC 8/07 64 The Staged LHC Path Energy density at collimators Stored energy in beams Number of collimators (nominal 7 TeV) State-of-the-art in SC colliders (TEVATRON, 1 MJ/mm2 2 MJ Phase 1 LHC Collimation 400 MJ/mm2 150 MJ 88 Nominal LHC 1 GJ/mm2 360 MJ 122 Ultimate & upgrade scenarios ~4 GJ/mm2 ~1.5 GJ ≤ 138 Limit (avoid damage/quench) ~50 kJ/mm2 ~10-30 mJ/cm3 HERA, …) RWA, SLAC 8/07 65 8) Conclusion • LHC advances the accelerator field into a new regime of high power beams with unprecedented stored energy (and destructive potential). • The understanding of beam halo and collimation of losses at the 10-5 level will be crucial for its success (high luminosity)! • LHC collimation will be a challenge and a learning experience! • Collimation is a surprisingly wide field: Accelerator physics, nuclear physics, material science, precision engineering, production technology, radiation physics. • A staged collimation approach is being implemented, relying on the available expertise in-house and in other labs. • The help from other labs, especially SLAC and LARP, is greatly appreciated. We must be sure to get the best possible system implemented! Bid for support from European Community (FP7). RWA, SLAC 8/07 66 Supporting Slides RWA, SLAC 8/07 67 Failure Impacts on Collimators (for Cu) Beam loss at the 10-5 level can damage components: Pre-fire of one dump kicker module (2.2 MJ) Asynchronous beam dump (miss dump gap) (0.5 MJ) Impact from one full batch at injection (2.3 MJ) Slow case: Impact during low beam lifetime (0.2 h to1 h) (4.4 MJ in 10s) Beam types: Protons and ions Full stored beam power: 360 MJ (7 TeV) Fast cases (< 1 turn): Energy to melt 1 kg Cu: 0.7 MJ Observations: • We expect losses on the 0.1% - 1% level. Sufficient to melt several kg Cu. • The 2002 LHC collimation system (Al/Cu) would withstand only on the 0.001% level! Note: Only one primary per plane. Disturbed beam can bypass primary and hit secondary (1 turn). Any collimator can be hit (don’t constrain LHC tune). RWA, SLAC 8/07 68 Peak Beam Loss Specification • The collimation system should handle the following loss rates: • Loss rates based on experience. Not too conservative: Peak loss at 7 TeV is 1% of beam in 10s! • Supported by Tevatron, HERA and RHIC experience! RWA, SLAC 8/07 69 Collimation project Resources/planning R. Assmann, O. Brüning, H. Schmickler, J. Lettry, M. Mayer Beam aspects R. Assmann, LCWG System design, optics, efficiency, impedance (calculation, measurement), beam impact, tolerances, diffusion, beam loss, beam tests, beam commissioning, operational scenarios, support of operation. (R&D phase 1&2) report to Leader: R. Assmann Project engineer: O. Aberle Organization, schedule, budget, milestones, progress monitoring, design decisions Energy deposition, radiation Engineering, production & HW support A. Ferrari (collimator design, ions) SC/RP (radiation impact) FLUKA, Mars studies for energy deposition around the rings. Activation and handling requirements. (R&D phase 1&2) O. Aberle (ring) Y. Kadi (transfer line) Conceptual collimator design, hardware commissioning, support for beam tests, series production, installation, maintenance/repair. (R&D phase 1&2) (S. Myers, LTC) LARP Collimation SLAC, BNL, FNAL Electronics, sensors, infrastructure controls R. Losito (motors, sensors, electronics, infrastructure, low level control) M. Jonker (control system and middleware) M. Lamont (top level controls application). Mechanical engineering (TS) Coord.: M. Mayer Engin.: A. Bertarelli Sen. designer: R. Perret Technical specification, mechanical integration, thermomechanical calculations and tests, mechanical design, prototype production&testing, drawings. (R&D phase 1&2) Installation & remote tools Beam instrumentation Dump/kickers/TL K. Kershaw (TS) B. Dehning B. Goddard Local feedback Machine Protection Electronics/radiation J. Wenninger R. Schmidt T. Wijnands RWA, SLAC 8/07 AB department Coll. vacuum design & production (AT) M. Jimenez Vacuum design at collimators, vacuum performance, vacuum interconnects at collimators (design, production, installation, commissioning), support for bake-out equipment. AT department TS department 70 Collimator Sketch A. Bertarelli, R. Perret et al RWA, SLAC 8/07 71 Effect of Closed Orbit (Static) Local inefficiency [1/m] Quench limit (nominal I, =0.2h) Higher inefficiency (factor 2) Less performance! Impact on machine design: Allocation of ring BLM’s! RWA, SLAC 8/07 72 Residual Dose Rates – TCP / TCSG / TCAPA / TCAPC One week of cooling S. Roesler et al LHC collimators and cleaning insertions optimized for radiation handling! RWA, SLAC 8/07 73 Thermal expansion [mm/ºC] CFC Material Properties (BNL tests) Non-radiated Radiated after annealing Radiated Temperature [ºC] N. Simos No change close to operating temperature in the LHC. Annealing… RWA, SLAC 8/07 74 Required Collimator Openings Aperture allowances: 3-4 mm for closed orbit, 4 mm for momentum offset, 1-2 mm for mechanical tolerances. Energy Location a [m] b [m] anorm [m1/2] anorm/e1/2 450 GeV Arc 0.012 180 8.8 × 10-4 10 7 TeV Triplet 0.015 4669 2.2 × 10-4 10 Collimator setting (prim) required for triplet protection from 7 TeV secondary halo: ~ 0.15 b coll acoll atriplet b triplet ~ 0.6 max Aprimary max A secondary Collimator gap must be 10 times smaller than available triplet aperture! Collimator settings usually defined in sigma with nominal emittance! RWA, SLAC 8/07 75 LHC Halo Scattering in collimator jaws (at 6/7 s) Transverse scattering angles + momentum loss Halo at zero dispersion Halo at max dispersion Betatron collimators generate a small off-momentum halo (singlediffractive scattering)! RWA, SLAC 8/07 76 Single-Diffractive Scattering Cross-section single-diffractive scattering: Comparison FLUKA – STRUCT – COLLTRACK/K2 LHC p collimation system was optimized until fundamental limitation was met: • Some protons experience single-diffractive scattering in primary betatron collimators: large energy offset and small betatronic kick. • Betatron collimators generate off-momentum halo. • Most of newly off-momentum protons are lost in first place with high dispersion: downstream dispersion suppressor. RWA, SLAC 8/07 77 BNL/LARP Radiation Tests on CFC Work done by N. Simos within LARP. 1020 p shot on CFC collimator material samples (identical material). Dose much higher than yearly dose on most exposed LHC collimators (~1016 p/year). Work in progress to extrapolate to LHC losses (FLUKA team). Serious DAMAGE of 2D CC after heavy irradiation exposure RWA, SLAC 8/07 78