Linac Commissioning P. Emma LCLS Commissioning Workshop, SLAC Sep. 22-23, 2004 LCLS P. Emma, SLAC LCLS Commissioning – Sep.
Download ReportTranscript Linac Commissioning P. Emma LCLS Commissioning Workshop, SLAC Sep. 22-23, 2004 LCLS P. Emma, SLAC LCLS Commissioning – Sep.
Linac Commissioning
P. Emma LCLS Commissioning Workshop, SLAC
Sep. 22-23, 2004 P. Emma,
SLAC LCLS
LCLS
Commissioning – Sep. 22, 2004
Linac Commissioning Document Available
>23 page DRAFT document describing: initial checkout setup of linac how/where to measure beam what device to scan and by how much expected resolution how/where to correct beam etc…
http://www-ssrl.slac.stanford.edu/lcls/linac/notes/linac_commissioning.ps
(not complete yet, but close) P. Emma,
SLAC
LCLS
Commissioning – Sep. 22, 2004
Linac ‘Commissioning’ (Physics)
Initial checkout (tunnel and beam-based) How to setup
I pk
= 3.4 kA, ge 1.2 m m, etc.
What to measure and what to adjust (simulations) Longitudinal phase space Bunch Length Energy Spread (proj. & slice) Transverse phase space Projected Emittance Slice Emittance
LCLS
Commissioning – Sep. 22, 2004 P. Emma,
SLAC
Initial Machine Conditions
Magnets warmed, standardized, and set properly Reasonable quality
e
beam available: Rough beam steering established Rough RF phasing of each klystron (1 or 2 deg) Any beam obstruction and loss issues solved P. Emma,
SLAC
LCLS
Commissioning – Sep. 22, 2004
Initial Checkout TUNNEL
Power-on polarity checks of all “new” magnets Validate proper cabling connections (magnets, BPMs, diagnostics…) Rough alignment inspection (tape measure, eye) Verify all insertable devices move in and out, and are finally removed P. Emma,
SLAC
LCLS
Commissioning – Sep. 22, 2004
Initial Checkout BEAM-BASED
Take full set of
x
and
y
‘oscillation’ data (checks optics and BPM scaling…) Verify all profile monitor scaling with known centroid shifts (wires, OTR, YAG, screens…) Repeat above at high dispersion points (DL1, BC1, BC2, DL2) using energy changes Calibrate all BPM-charge, and toroid readings based on one well established reference Document all the above for future scrutiny CHECKOUT
MUST BE COMPLETE
BEFORE MEASUREMENTS AND TUNING BEGIN!
P. Emma,
SLAC
LCLS
Commissioning – Sep. 22, 2004
Location of Main Linac Diagnostics
5+ energy spread meas. stations (optimized with small 5+ emittance meas. stations designed into optics (
D b
)
y
x
,
y ) BPMs at or near most quadrupoles and in each bend syst.
RF deflectors for slice
e
and
s
E measurements (L0 & L3)
rf gun
T-cav.
ge
x
,
y
ge
x
,
y ...existing linac
s
E
E
L1 X s
E
E
L2 ge
x
,
y
T-cav.
s
E
E
L3 ge
x
,
y
ge s
E
E
x
,
y
P. Emma,
SLAC
LCLS
Commissioning – Sep. 22, 2004 s
E
E
Setup of Linac-0 RF
s
y
= bunch length Establish initial bunch length Phase linac-0
RF-deflector at 1 MV
minimize energy spread with L0 RF phase
RF-deflector
P. Emma,
SLAC
Phasing L0-Linac
LCLS
Commissioning – Sep. 22, 2004
20 m m res. BC1 BPM
Setup of Linac-1 RF
20 m m res. BC1 BPM LX RF phase L1 RF phase
rf gun
Linac-1 RF phase scan (X-band off, BC1 bends at 295 MeV) Linac-X RF phase scan (BC1 bends at 250 MeV)
set phase to
-
25 ˚
0.5
˚ Linac-1
21-1b 21-1d X
set phase to
-
160˚
0.5
˚
Turn on BC1 energy feedback Switch off BC2 chicane Use sec-25 RF-deflector to meas. bunch length ( s
z
1 ) Adjust S-band RF phase ( 0.5
˚) to set s
z
1 195 10 m m P. Emma,
SLAC
LCLS
Commissioning – Sep. 22, 2004
40 m m res. BC2 BPM
Setup of Linac-2 RF
5 m m res. LTU BPM (NO CSR) L2 RF phase L2 phase L2 Linac-2 RF phase scan (BC2 bends at 5.9 GeV, or…)
set phase to
-
41 ˚
0.5
˚
L3 Scan Linac-2 phase & use LTU BPM to find max. wake-induced energy loss across Linac-3 Turn on BC2 energy feedback Use sec-25 RF-deflector to measure length ( Adjust L2 RF phase ( 0.5
˚) to set Linac-3 phasing is trivial ( 5˚) s
z
2 20 s
z
2 ) 2 m m P. Emma,
SLAC
LCLS
Commissioning – Sep. 22, 2004
Emittance Meas. Simulation in LCLS
Multiple OTR screens Multiple wire-scanners Quad-scans on single OTR Quad-scans on OTR with RF-deflector OTR1,2,3
BC1
WS11,12,13 P. Emma,
SLAC
LCLS
Commissioning – Sep. 22, 2004
135-MeV OTR
x
-profiles from tracking
s
x
118 m m s
x
49 m m P. Emma,
SLAC
s
x
120 m m non-Gaussian ge
x
= 0.75 ± 0.04 m m
LCLS
Commissioning – Sep. 22, 2004
x
-Slice-Emittance Measurement
s
y
RF-deflector at 1 MV
bunch length
slice OTR 10 times P. Emma,
SLAC
“QE03” quad scanned
LCLS
Commissioning – Sep. 22, 2004
x
-Slice-Emittance Measurement Simulation
“QE03” scanned 20% (centered on 106% of its nominal gradient)
Injector at 135 MeV with S-band RF-deflector at 1 MV
(same SLAC slice e code used at BNL/SDL) = meas. sim.
= calc.
=
y
distribution = actual DL1 slice-emit on WS02 P. Emma,
SLAC
slice-5
LCLS
Commissioning – Sep. 22, 2004
y
-slice-Emittance Measurement in BC1
“Q21201” scanned ±20% P. Emma,
SLAC
3.9 mm
LCLS
Commissioning – Sep. 22, 2004
y
-slice-Emittance Measurement Simulation
“Q21201” scanned 20% (centered on 92% of its nominal gradient)
slice-
y
emittance in BC1 using
x
-chirp
= meas. sim.
= calc.
=
y
distribution = actual P. Emma,
SLAC
slice-5
LCLS
Commissioning – Sep. 22, 2004
Empirical BC1/BC2 Dispersion Correction
actual data from SPPS chicane D y
x
/2
Residual
x
-dispersion (and its angle) is precision minimized using ‘tweaker’ quads in the chicane Correct
h
and (
ah + bh
), orthogonally with 2 quads
P. Emma,
SLAC
SPPS chicane with quads
LCLS
Commissioning – Sep. 22, 2004
Transverse Wakefield Compensation
All quadrupoles, RF structures, and BPMs misaligned by 300 m m rms Small ‘bumps’ added to correct emittance trajectory after steering steering coils P. Emma,
SLAC
ge
x
ge
y
2.1 m m 5.2 m m
LCLS
Commissioning – Sep. 22, 2004 ge
x
ge
y
1.0 m m 1.1 m m
Repeat for 100 Different Seeds
M. Borland D e / e 20% (projected) P. Emma,
SLAC
LCLS
Commissioning – Sep. 22, 2004
Energy Jitter Measurement (Feedback)
Two 5 m m BPMs:
x
1
x
2 relative energy centroid resolution: ~0.003% undulator… ( h
x
125 mm) Difference of BPM
x
-readings is proportional to energy change, and insensitive to incoming trajectory jitter.
P. Emma,
SLAC
LCLS
Commissioning – Sep. 22, 2004
Slice-Emittance Configuration for LTU
nominal optics (proj. emit.) WS31-34 undulator… P. Emma,
SLAC
slice-emit.
meas. optics OTR33 stopper inserted
LCLS
Commissioning – Sep. 22, 2004
Slice-Emittance Measurements in LTU
“QEM3” (or tweaker) scanned 3% (centered on its nominal gradient)
LTU at 14 GeV with S-band RF-deflector at 24 MV
z
P. Emma,
SLAC
y
= meas. sim.
= calc.
=
y
distribution = actual
LCLS
Commissioning – Sep. 22, 2004
Slice Energy Spread Measurements in LTU
s
E
/
E
10 4
LTU at 14 GeV with S-band RF-deflector at 24 MV
s
x
12
m
m
P. Emma,
SLAC
FEL goal
LCLS
Commissioning – Sep. 22, 2004
Summary
Most diagnostics incorporated into design and simulated (1 st pass) Two RF-deflectors allow time resolved measurements at low and high energy Tune-up algorithms considered, but more refinement needed Feedback systems must maintain setup while tuning progresses (bunch length monitors?)
LCLS
Commissioning – Sep. 22, 2004 P. Emma,
SLAC