romatsa - MoldATSA

Download Report

Transcript romatsa - MoldATSA

Overview of existing ROMATSA ATM system and plans for the future

Summary

    

Core activities Facts and figures Strategic axes Operational concept Strategic Action Lines

ATM - main objectivesCNS - main objectives o Communication Systems Modernization o Navigation Systems Modernization o Survellaince Systems Modernization

September 24 , 201 2 ROMATSA Presentation KISHINEV 2

Core activities

Provision of ANS for the Romanian Airspace:

• Air Traffic Services • Communication, Navigation and Surveillance • MET services • Aeronautical Information Services • Civil Military Coordination • Search & Rescue Coordination Center September 24, 2012

Air Traffic Services Units

• 4 AROs / 16 TWRs • 3 APPs • 1 ACC ROMATSA Presentation KISHINEV

AIS / MET Services

• MET Offices; • 13 MET Self Briefing Offices; • 1 MET Watch Center • 4 ARO/BRIEFING Offices 3

Facts and figures

Evolution of the en-route unit rate 2007– 2011

Evoluţia tarifului unitar de rută al României în perioada 2007-2011

60 50 150,56 lei 44.99

41.38

Tarif unitar aprobat Tarif unitar aplicat

46.46

168,10 lei 196,84 lei 46.44

44.32

42.19

188,86 lei 44.33

44.74

39.39

40 30 20 10 0 2007 2008* 2009* 2010* 2011*

An

* Începând cu anul 2008 tariful unitar de rută este stabilit în moneda naţională. Tarifele unitare efectiv aplicate în perioada 2008-2011 au fost ajustate lunar în funcţie de variaţia cursului REUTERS leu/euro mediu lunar de închidere al lunii precedente faţă de cursul de referinţă folosit la calculul tarifului unitar aprobat (cursul REUTERS leu/euro mediu lunar de închidere al lunii septembrie a anului anterior: 3,34691 sept. 2007 pentru 2008, 3,61823 sept. 2008 pentru 2009, 4,23833 sept. 2009 pentru 2010 şi 4,26025 sept. 2010 pentru 2011).

September 24 , 201 2 ROMATSA Presentation KISHINEV 4

Facts and figures

Evolution of the en-route chargeable service units 2007– 2011

în perioada 2007-2011

4,000 3,434 3,500 3,304 3,144 3,135 3,008 3,000 2,500 2,000 1,500 1,000 500 0 2007 2008 2009 2010 2011

An

Traffic in Romania increased by 3.96% during Summer 2011 (May to October), when compared to Summer 2009 September 24 , 201 2 ROMATSA Presentation KISHINEV 5

Facts and figures

Evolution of the en-route chargeable service units btwn 2008-2011 compared to 2007

în perioada 2008-2011 faţă de anul 2007

120.00% 109.24% 105.08% 100.00% 100.00% 99.73% 95.69% 80.00% 2007 September 24, 201 2 2008 2009 ROMATSA Presentation KISHINEV 2010 2011

An

6

STATFOR traffic forecast

for 2011 – 2015

800,000

Romania - Annual IFR Movements

700,000 600,000 500,000 400,000 300,000 200,000 100,000 IFR movements - Actuals IFR movements - Baseline forecast IFR movements - High forecast IFR movements - Low forecast 0

Annual growth

H B L 2006 A

2006

o.4% 2007 A

2007

-1.9% 2008 A

2008

0.1% 2009 A

2009

-3.3%

2010

9.0% 2010 A

2011

2.6% 1.5% 0.5% 2011 F

2012

5.5% 4.2% 3.1% 2012 F

2013

7.3% 5.3% 4.2% 2013 F

2014

7% 5.4% 4.5% 2014 F

2015

6.6% 5.2% 4.4%

2016

6.6% 5.2% 4.3% 2015 F

AAGR 2016/ 2010

5.9% 4.5% 3.5% September 24 , 201 2 ROMATSA Presentation KISHINEV 7

Strategic axes

Services provision in a smooth, safe and efficient manner Modernization of the ATM system as per SES requirements on systems interoperability (i.e. IP1 Deployment) Improvement of the air navigation services performance supporting the EU performance targets Ensure the establishment of DANUBE by December 4, 2012

September 24, 201 2 ROMATSA Presentation KISHINEV 8

Operational Concept

 

1 ACC in BUCHAREST ATC Center

Transfer of en-route activity from CONSTANTA ATC

Center to BUCHAREST ATC Center (finalized 2010)

Transfer of en-route activity from ARAD ATC

Center to BUCHAREST ATC Center (2012) Establish CONSTANTA Terminal control area and APP CONSTANTA Traffic Unit - (finalized 2010)

Establish ARAD Terminal control area and APP ARAD Traffic Unit - (finalized Mar. 2012)

September 24, 2012 ROMATSA Presentation KISHINEV 9

Operational Concept

  

Redesign and equip APP in BUCHAREST ATC Center for the necessary infrastructure (finalized Apr. 2012) APP CLUJ in BUCHAREST ATC Center - (2013) FIC upgrade in FIR/ Bucharest ATC Center

Operational Concept

Provision of means and procedures for special situations to facilitate the transfer of the entire en-route activity to ACC Bucharest

• • Establishment of CR1 (Contingency Room) in Bucharest TDS Room Establishment of CR2 by agreement with MoD September 24, 2012 ROMATSA Presentation KISHINEV 11

Operational Concept

16 TWRs 3 APPs 1 ACC in 2 ATC centers 4 ARO/BRIEFING offices Aeronautical MET Services: •16 MET offices •13 MET Self Briefing offices • 1 MET Watch Center

Strategic action lines

Single European Sky & DANUBE FAB

Performance of the provision of the air navigation services Organization and flexible use of the airspace Interoperability

September 24, 2012

OBJECTIVES

ROMATSA Presentation KISHINEV

Pro-active cooperation in ANS domain

13

Strategic action lines

ATM – Main objectives Phase 1 – Definition

• Estimated Time: End 2012 • Develop operational - technical safety and functional specifications of ROMATSA 2015+ ATM SYSTEM • Prepare and launch a tender to replace the current system • Approval of the tender documentation and specifications.

• Open tender

Phase 3 – Transfer into operations Phase 2 – Development

• Estimated Time: End 2013 • Development of ATM system – software and hardware • System Interface Development • Verification, validation, testing • Systems Integration • Implementation of management plans • Operational and technical documentation • Estimated Time: December 2014 • FAT activities, system installation and SAT • Transfer plan: technical and operational preparation and safety assessment • Formal authorization for putting into service • Operational transfer (shadow, trials, contingency)

According to:

 Interoperability of the ATM ROMATSA System  ROMATSA 2015+ ATM System September 24, 2012 ROMATSA Presentation KISHINEV 14

Strategic action lines

Capacity

LRBBCTA - Capacity profile and demand

200 180 160

NO PROBLEMS ARE FORESEEN FOR ACC BUCHAREST

140 120 100 80 60 40 20 0 2011-2015 Reference Capacity Profile Demand / Shortest Routes - Peak 3 Demand / Current Routes - Peak 3 Demand / Shortest Routes - Peak 1 Capacity Baseline September 24, 2012 2010 106 108 119 183 2011 183 113 115 126 ROMATSA Presentation KISHINEV 2012 183 120 121 133 2013 183 126 127 141 2014 183 133 135 149 2015 183 141 142 156 15

“Save one minute” initiative

“DIRECT TO” September 24, 2012 ROMATSA Presentation KISHINEV 16

“Save one minute” initiative “Direct to“ – Estimated Savings

Daily total savings

(estimated) No of flights 469 Distance 216 NM Time 29 min.

Fuel quantity 71695 Kg CO 2 225840 Kg

Yearly average savings

(estimated) No of flights Distance Time 168840 77760 NM 174 hours 7 days 6 h September 24, 2012 ROMATSA Presentation KISHINEV Fuel quantity 25.8 mil. Kg CO 2 81.3 mil. Kg 17

Strategic action lines

CNS – main objectives

ground-air ground communica tions ground-to ground communicati ons COMMUNICATION SYSTEMS MODERNIZATION As of February 2015, the modernized ground-air-ground communication infrastructure will allow the use of the data-link services (CPDLC) on route and in the terminal areas based on VDL mode 2 protocol in accordance with the operational requirements and specifications developed in this respect DATA LINK PROJECT

• Elaboration of operational concept • Elaboration of operational, technical and safety requirements • Fast-time and real-time simulations • Elaboration of technical project • Safety analysis • Staff training • Integration and putting into service of system September 24, 2012 ROMATSA Presentation KISHINEV 18

Strategic action lines

CNS – main objectives

Communication systems modernization ground-air-ground communications

by 2015 a new modernization stage, started in 2010, for the ROMATSA Comm. Network (STcR) will be finalized The ROMATSA Comm. Network Project (STcR) started in 2000, in order to

  Enable full compliant ATM services over a multiservice converged network which integrates voice (including VoIP) and data communications, securely and reliably Easily manage communications network: 

one network

instead of multiple separate networks 

one technology

instead of multiple technologies  Dramatically cutting costs and enhance flexibility and manageability of communications services September 24, 2012 ROMATSA Presentation KISHINEV 19

Strategic action lines

CNS – main objectives

Communication systems modernization ground-air-ground communications

  

The STcR:

  

Was Carefully designed and tested

providers (Cisco Gold Partner) together with awarded high quality solution

Is a Mature

(in terms of proven performances and safety) network technologies and equipments used Continuously monitored and enhanced for better performance and higher safety in operation

by 2015 the VCSS in the Bucharest ATC Center will be modernized to support VoIP By 2015 new VHF equipments will be installed in all en route sites to support VoIP

Strategic action lines

CNS – main objectives

  IP core network transporting data and voice is supported by ccommunication services leased from

2 national carriers and the 3 2013 rd one will be operational in

Main IP network nodes are connected in mesh topology, using 2Mbps links, in order to improve redundancy TWR Cluj TWR S Mare 12 8 128 DSNAR Cluj 8 12 128 8 12 TWR Sibiu 12 8

DSNAR Bacau/ TWR Bacau

8 12 TWR Iasi 128 128 TWR Oradea 64 8 1 2 TWR Arad 8 12 8 12 1 2 8

DR Arad

12 8 12 8 TWR Caransebes 64K TWR Craiova 2 5 2 6 5 6 128 128

VPN

4 6 K 2 5 6 2Mbp s

CDZ Bucuresti

64 256 256 64K Otopeni 2 2 5 6 5 6

DR Constanta

RTC K TWR Tulcea CE Topolog September 24, 2012 ROMATSA Presentation KISHINEV 21

Strategic action lines

CNS – main objectives

New modernization stage of STcR creates:

        Two level for communication process: Backbone level: routers for WAN level data exchange between the main network nodes.

Access level: routers for data exchange between the backbone and the final users voice, RADAR, DPS, AFTN, LAN, MET and others.

Higher flexibility in order to: Increase internal data processing capacity Improve availability, safety and security by reducing the number of tasks/router. Less task unavailable in case of router failure.

Simple maintenance procedures.

Increase flexibility to add new dedicated functionalities regarding security and monitoring for backbone routers, like: intrusion detection, network traffic analysis, Firewall.

Backbone

Core level

Access

level September 24, 2012 ROMATSA Presentation KISHINEV 22

Strategic action lines

CNS – main objectives

Communication systems modernization

ground-air-ground communications ATC Ground-Ground leased lines for ACC Bucharest

 

CDZ Bucharest:

 

1 MFC analog - Lviv (BACAU and NAPOC sectors)

1xE1 link Sofia (MFC, Radar, OLDI, AFTN, others)   1 Sofia + 1 Varna (old analog line) 1 Budapest (old analog line)  

1x64kbps (modem) Odessa OLDI 1x64kbps Chisinau Radar data (via Bacau) CDZ Constanta:

  

1 MFC analog - Chisinau (BACAU and DINSI sectors) 1 MFC analog - Odessa (DINSI sector) 1 MFC analog - Simferopol (DINSI sector)

  1xE1 link Varna (MFC, Radar, OLDI, AFTN, others)

CDZ Arad:

 1 MFC analog Belgrad  1xE1 link Budapest: 2 MFC (2x64kbp channels), OLDI and Radar September 24, 2012 ROMATSA Presentation KISHINEV 23

Strategic action lines

CNS – main objectives

 

Communication systems modernization ground-air-ground communications

ROMATSA PROPOSALS for International voice & datalinks between ROMATSA, MoldATSA and UkSATSE in order to improve support for MFC, AFTN, OLDI and radar data exchange:  Installation of the main and back-up digital circuits (2Mbps or nx64kbps circuits) between ANSPs and ROMATSA     Establish necessary communication equipment (other than that provided by the telecom company) to implement new digital circuits and links between ACCs. Digital circuits cost analysis LoA amendments to include digital circuits support for voice and data (OLDI, and radar) Analysis of the possibility to use existent digital infrastructure with common neighbors (Hungary, Slovakia, Bulgaria) as back-up for the new digital lines .

September 24, 2012 ROMATSA Presentation KISHINEV 24

SAR – Search and rescue

Communication

ROMATSA SAR COMMUNICATION ARHITECTURE PSTN TETRA

Gateway PSTN redundant Gateway TETRA redundant Central location IP Call Centre Cluster Active/ Standby Recording and communication servers Switch Gigabit Ethernet SAR+GIS servers Hub Hub

Backbone STS

ROMATSA Site operator National unique system for emergency calls - 112 ARL September 24, 2012 Site operator Site 1 Spoke Spoke Site operator Site 2 ROMATSA Presentation KISHINEV Spoke Site operator Site N 25

SAR – Search and rescue

IT

ROMATSA SAR IT ARHITECTURE

September 24, 2012 Server 1 AD Server 1 Communication and recording SAR COORDINATION CENTER FC FC FC wkstation1 wkstation2 wkstation3 WAN Switch Gigabit Ethernet Switch Gigabit Ethernet Server 2 Communication and recording FC FC FC Server 1 GIS & SAR FC FC Switch Fibre Channel FC Switch Fibre Channel Storage Area Network FC Server 2 GIS & SAR SAS Backup unit Antivirus and backup Server Server 2 AD Sites operators ROMATSA Presentation KISHINEV 26

Strategic action lines

CNS – main objectives

NAVIGATION SYSTEMS MODERNIZATION

 RNAV Infrastructure development for PBN (DVOR/DME):    ROMATSA has implemented appropriate terrestrial infrastructure to support en-route and TMA RNAV operations.

In order to improve DME-DME coverage: navigation  in the center of Romania (Cluj TMA), 4 new en-route DME systems were installed in 2011.

 in the Eastern part of Romania, 2 new en-route DME systems are planned to be installed in 2012 and 2013 in Iasi and Bacau.

In order to maintain availability of existing VOR/DME systems ROMATSA planned to replace:  By 2013, last 2 CVOR/DME systems with new DVOR/DME systems  By 2015, 9 old DVOR/DME with new DVOR/DME systems September 24, 2012 ROMATSA Presentation KISHINEV 27

Strategic action lines

CNS – main objectives

NAVIGATION SYSTEMS MODERNIZATION

   In 2011 ROMATSA and BULATSA has signed an agreement on shared use of radio navigation aids for area navigation between Romania and Bulgaria.

Future development of the Romanian en-route NAV infrastructure will be designed at DANUBE FAB level.

In order to rationalize NAV aids infrastructure for PBN, ROMATSA:  Planned for withdraw all NDBs for en-route, by 2013   Replaced in 2011, 20 NDBs for terminal navigation services. The NDB systems were replaced in order to maintain non-precision back-up procedures for approach and landing.

4 old NDB systems for terminal navigation services will be withdrawn in 2013.

September 24, 2012 ROMATSA Presentation KISHINEV 28

Strategic action lines

CNS – main objectives

NAVIGATION SYSTEMS MODERNIZATION

September 24, 2012 ROMATSA Presentation KISHINEV 29

Strategic action lines

CNS – main objectives

SURVEILLANCE SYSTEM MODERNIZATION - Schedule

2012

Modernization of Mode S – radar sensors MSSR Bucharest

2012

Putting into service WAM TRANSYLVANIA (Sibiu, Tg. Mureş)

2012

Modernization of Mode S – radar sensors MSSR Arad and Constanta

2013

Putting into service A-SMGCS system Bucharest Otopeni

2015 -2016

Replacement of PSR/MSSR TMA Bucharest September 24, 2012

2014 -2015

Modernization of Mode S – radar sensors MSSR Cluj

2014-2015

Extension WAM MOLDOVA ROMATSA Presentation KISHINEV

2016

Putting into service ADS – B pilot system in FIR BUCHAREST 30

Strategic action lines

CNS – main objectives

SURVEILLANCE SYSTEM MODERNIZATION

 A-SMGCS system at Otopeni TWR  Mode S radars sensors - installed  Improve radar coverage – multilateration - installed  Optimize the protection of radar data supplied by civil and military radar sensors in civil and military coordination systems  Improve the surveillance service using ADS-B type solutions September 24, 2012 ROMATSA Presentation KISHINEV 31

Strategic action lines

CNS – main objectives

Surveillance system - infrastructure ROMATSA has 8 radars:

3 MSSR Mode S Radars

Bucharest Constanta Arad

The three radars became operational in 2012

 

4 MSSR Mode A/C Radars 1 PSR/MSSR Mode A/C Radar Buciumeni Topolog Bacau Cluj – 1994 - 1994 - 2000 - 2000 Otopeni – 1994/2000

September 24, 2012 ROMATSA Presentation KISHINEV 32

Strategic action lines

CNS – main objectives

Surveillance system - infrastructure ROMATSA also installed a Wide Area Multilateration System (WAM TRANSYLVANIA) which became operational from 2012

WAM system provides radar coverage for the new Cluj TMA which is located in central part of Romania between the Carpathian Mountains. Difficult terrain and layout of Cluj, Târgu Mureş and Sibiu airports, situated in the lowlands between hills, necessitated the adoption of a multilateration solution to ensure operational requirements at very low altitudes, practically from the runway level.

September 24, 2012 ROMATSA Presentation KISHINEV 33

New CLUJ TMA

September 24, 2012 ROMATSA Presentation KISHINEV 34

WAM COVERAGE at FL 100 for CLUJ TMA

September 24, 2012 ROMATSA Presentation KISHINEV 35

RADAR DATA SHARING

To fulfill the multiple radar coverage requirements in order to ensure 5 NM separation, ROMATSA concluded bilateral agreements to exchange radar data with: SERBIA – LOA 2012 HUNGARY – LOA 2010

MOLDOVA

- LOA 2005 BULGARIA – LOA 2005 and Romanian Air Force – LOA 2007 September 24, 2012 ROMATSA Presentation KISHINEV 36

www.romatsa.ro

September 24, 2012 ROMATSA Presentation KISHINEV 37